# Transformer sizing and load profiles | Kestvan

Build a transformer enquiry from demand, power factor, duty cycle and site conditions. Understand kVA, rated current and the information needed for review.

Canonical page: https://kestvan.com/guides/transformer-sizing-load-profile

[Kestvan](https://kestvan.com/)

[Technical knowledge](https://kestvan.com/knowledge-center)

[All technical guides](https://kestvan.com/knowledge-center)

A rating depends on the load and operating conditions. Connected equipment alone does not determine the required kVA.

Reviewed 14 November 2026

## Related equipment

[Oil-immersed transformers](https://kestvan.com/products/oil-transformers)

[Dry-type transformers](https://kestvan.com/products/dry-type-transformers)

[Project preparation assistant](https://kestvan.com/project-assistant)

## The practical answer

Send a time-based demand profile, supply details and site conditions before fixing the transformer rating.

## Translate demand into apparent power

Use electrical input demand, not motor shaft output or building area. At a defined operating point, S(kVA) = P(kW) / PF; match the power-factor and load-data bases.

- Separate connected load from simultaneous demand. Record which equipment actually runs together and where demand data were measured.
- For a balanced three-phase system, line current is I(A) = S(kVA) / [√3 × U(kV)], with U the line-to-line voltage on the winding being assessed.
- For substantial harmonics, true power factor and displacement cos φ are different quantities. Do not silently use one in place of the other.
## Describe the operating cycle

Provide normal, peak, standby and future cases, including durations. State whether standby capacity serves all loads or only essential circuits.

- Identify large motor starts, their starting method and the acceptable voltage disturbance; steady-state kVA alone does not check starting performance.
- Describe converter, UPS, charging and other non-linear loads, with available harmonic data and manufacturer requirements.
- State expansion and redundancy separately. A universal spare-capacity percentage is not a substitute for the project's operating and thermal review.
## Check the rating against the installation

Oil-immersed and dry-type designs need different thermal assessments. Actual ambient conditions, altitude, enclosure ventilation and cooling mode affect the usable rating; adding a fan does not establish a guaranteed higher rating.

- Declare primary and secondary voltages, frequency, phase arrangement, tap requirements and the intended earthing system.
- A 60 Hz design is not automatically suitable for operation at the same voltage on 50 Hz. Obtain a design-specific voltage/frequency assessment.
- Request the agreed cooling ratings and supporting thermal evidence. Mineral-oil and dry-type loading guides address ageing under defined temperature and loading conditions; they do not provide a universal overload allowance.
## Create a reviewable technical schedule

Separate confirmed values and open items, so equipment, installation and commercial proposals use the same assumptions.

- Attach the single-line diagram, demand profile, existing transformer nameplates and any utility specification relevant to the connection.
- Ask for guaranteed losses, impedance, temperature-rise basis, connection group, dimensions and terminal interfaces for the proposed design.
- Name the required standard editions and deviations in the technical agreement. General reference information is not a project-specific rating or utility approval.
## Inputs to prepare

- Demand in input kW or measured kVA, with the measurement basis
- True power factor and available harmonic information
- Normal, peak and standby load durations
- Supply voltages, frequency, phases and earthing arrangement
- Altitude, ambient conditions, enclosure and cooling
- Expansion, essential-load and utility requirements
## Common specification mistakes

- Adding every nameplate rating and treating the sum as simultaneous demand
- Using one loading percentage or spare margin for every project
- Selecting kVA before checking frequency, thermal conditions and starting loads
## Questions from project buyers

### Does 1,000 kVA mean 1,000 kW is available?

Only at power factor 1 for that operating point. Real-power demand, power factor and other loading constraints must be considered together; kVA is not an unconditional kW guarantee.

### Can I choose a standard rating from a load calculation alone?

It is a starting point. Starting duty, harmonics, ambient conditions, cooling, redundancy and the utility interface must also be reviewed before the final rating is agreed.

## Standards & further reading

- [IEC 60076-1:2011 — General](https://webstore.iec.ch/en/publication/588)
- [IEC 60076-7:2018 — Mineral-oil transformer loading](https://webstore.iec.ch/en/publication/62459)
- [IEC 60076-12:2008 — Dry-type transformer loading](https://webstore.iec.ch/en/publication/592)
- [Transformer selection and load profiles](https://www.electrical-installation.org/enwiki/Choice_of_MV/LV_transformer)
These guides support project definition. Final ratings, protection settings, installation and acceptance criteria require the project engineer’s review against the applicable specification and local rules.

[Discuss your equipment requirements](https://kestvan.com/contact)

[Project preparation assistant](https://kestvan.com/project-assistant)

[Transformer full-load current: formula and 100–2,500 kVA reference values](https://kestvan.com/guides/transformer-full-load-current)