The practical answer
Compare rated current, fault withstand and interrupting duty separately. Confirm the required protection scheme, access conditions and evidence for the actual assembly before accepting an equipment offer.
Start at the connection point
State operating voltage, highest system voltage, frequency and the available fault study. A radial feeder and a ring supply need different operating arrangements; a ring-main unit label does not establish how a network will be protected. Record normal and contingency configurations, including future parallel sources.
- Identify incomers, bus sections, transformer feeders, metering and earthing functions.
- Ask the utility to confirm connection, protection and metering requirements.
Separate continuous and fault ratings
Continuous current concerns normal loading. Short-time withstand current includes a stated duration; peak withstand, making duty and breaking duty describe different fault stresses. An identical kA number does not make two ratings interchangeable. For LV equipment, distinguish the breaker rating at its operating voltage from the short-circuit capability of the complete assembly.
- Request the current value, duration and applicable test evidence together.
- Review protection clearing times against the equipment and cable withstand.
Define access and service continuity
For applicable MV assemblies, request the specified service-continuity category, partition arrangement and internal-arc classification. Read these alongside the tested accessibility, sides, current, duration and installation arrangement. They address different properties; enclosure IP is not an internal-arc classification. Cable entry, pressure relief and room layout must match the selected equipment.
- Confirm which compartments may be accessed and under what isolation conditions.
- Record maintenance access, interlocks and the intended operating procedure.
Make the offer technically comparable
Define relay functions, CT/VT duties, auxiliary supply, trip/close circuits, remote signals and communication interfaces. Specify insulating medium explicitly and assess destination requirements where relevant. Standards identify the assessment framework; they do not prove that every listed model has the same tested configuration or local approval. For LV assemblies, use IEC 61439-1 with the applicable product part, typically IEC 61439-2 for power switchgear and controlgear assemblies.
- Ask for an approved single-line diagram, rating schedule and deviations list.
- Agree assembly verification, routine tests and project witness points.
Inputs to prepare
- Connection voltage and frequency
- Maximum and minimum fault-study inputs
- Feeder schedule and normal switching state
- Protection, CT/VT and auxiliary supply
- Access, enclosure and installation conditions
- Specified standards, evidence and acceptance plan
Common specification mistakes
- Selecting by cabinet name or rated voltage alone.
- Treating breaking current, short-time withstand and peak current as the same rating.
- Using a component certificate as proof of the complete switchgear package.
Questions from project buyers
Does a higher current rating solve every short-circuit requirement?
No. Continuous current, short-time thermal duty, peak electrodynamic duty and switching duty must each be checked against the network study and the operating arrangement.
Can a standard reference confirm local utility acceptance?
No. The project must identify the applicable edition, local requirements, tested configuration and utility approval process. A published standard reference is not an approval certificate.