The practical answer
Agree the inspection and test plan before manufacture, then match each delivered serial number to its approved drawings and test records.
Define the acceptance basis first
Freeze specifications, drawing revisions, standard editions, guarantees and acceptance criteria before testing. The inspection/test plan defines review, witness or hold points, responsibilities and deviation closure.
- Distinguish routine results for delivered units from type or special-test evidence for a relevant design. Test classification depends on the applicable product standard and specification.
- A FAT is an agreed acceptance activity, not an additional product certification or proof that site installation is complete.
- An ISO management-system certificate does not certify the ordered transformer model. Check the scope and relevance of every supporting document.
Review records that identify the unit
Connect order, nameplate, approved drawing and report by serial number. A product-family heading alone does not identify measurements on the delivered unit.
- Review applicable winding resistance, ratio and phase-displacement, no-load loss/current, impedance and load-loss records against the agreed design.
- For applicable dielectric tests and dry-type partial-discharge results, request the test designation, conditions, outcome and criteria. The exact programme is design- and standard-dependent.
- For liquid-filled units, identify applicable liquid, leak or pressure, tap-changer and accessory checks. Record instrument identification and calibration evidence relevant to the tests.
Compare results on the same conditions
Record the relevant winding, terminals, tap, voltage, frequency, current and temperature. Distinguish measurements from results corrected to the agreed reference.
- Do not directly compare oil-transformer load losses at 75°C with dry-type reference values at 120°C. Align the temperature basis and other rating conditions first.
- State guaranteed losses and impedance together with applicable tolerances and correction methods. A generic pass stamp does not resolve an unexplained deviation.
- A routine impedance measurement is not evidence by itself of short-circuit withstand. Supporting design documents must match the evidence scope agreed in the contract.
Close the transport-to-site handover
Factory acceptance cannot detect later transport or installation damage. Record receipt condition and complete agreed site, accessory and interface checks before project authorization to energize.
- Site tests must follow the actual equipment manual and approved procedure, performed by qualified personnel. There is no universal insulation-resistance threshold or site dielectric voltage for every transformer.
- Keep transport and installation observations, factory-to-site comparisons, functional checks and unresolved items in one handover record.
- Deliver the approved drawings, serial-specific reports, operating and maintenance instructions, accessory information and agreed spares list; name the person responsible for each open item.
Inputs to prepare
- Approved technical schedule, drawings and standard editions
- Inspection/test plan, acceptance criteria and witness points
- Delivered serial numbers linked to nameplates and reports
- Measured conditions, reference corrections and instrument evidence
- Applicable design/type/special-test documents and their scope
- Site records, closed deviations and authorized handover
Common specification mistakes
- Treating a management-system certificate as model certification
- Comparing loss figures with different temperature or rating bases
- Treating FAT attendance as completed site acceptance or permission to energize
Questions from project buyers
Does a previous type-test report replace routine reports?
No. Design evidence and delivered-unit records serve different purposes. Check relevance and the serial-number traceability required by the purchase specification.
Must all factory tests be repeated at site?
Not automatically. The site programme depends on the equipment, transport and installation conditions, manufacturer instructions and approved project procedure. Agree its scope and criteria before delivery.