Prepared by Mingyu Ma · Sales Manager · Kestvan
A transformer quotation is easier to review when the offered design, its supporting documents and the unresolved differences are recorded together. Use this checklist after receiving a proposal; use the RFQ guide when preparing the initial enquiry.
This checklist supports sales and project coordination. Technical acceptance, design approval and agreed tests are confirmed by the responsible project parties.
Keep three kinds of values separate
- Reference
- A published catalogue or example value, tied to its stated model and conditions. It is a comparison starting point.
- Guaranteed
- A value expressly offered and agreed for the selected equipment in the project technical documents. Record its conditions and document revision.
- Unconfirmed
- An unanswered requirement, missing value or unresolved difference. Keep it open until the responsible party confirms it.
First fix the comparison basis
Compare the same equipment duty, quantity, rated voltages and frequency. Keep winding connection, tapping, impedance, cooling and site conditions visible. Match no-load and load losses to their units and reference temperature; a catalogue model name alone does not define the complete offer.
A working comparison sheet
Copy this blank structure into your project review. The prompts below describe what to check, not an equipment offer or a set of guaranteed ratings.
| Check | Buyer requirement | Offered value / status | Evidence / revision | Deviation / next action |
|---|---|---|---|---|
| Equipment, rated power and quantity | To complete | To complete | To complete | To complete |
| Primary / secondary voltage and frequency | To complete | To complete | To complete | To complete |
| Connection, tapping and impedance | To complete | To complete | To complete | To complete |
| Losses, units and reference conditions | To complete | To complete | To complete | To complete |
| Cooling, temperature rise and site conditions | To complete | To complete | To complete | To complete |
| Enclosure, dimensions and terminal interfaces | To complete | To complete | To complete | To complete |
| Applicable standards and project specification | To complete | To complete | To complete | To complete |
| Test scope and model-matched documents | To complete | To complete | To complete | To complete |
| Approval drawings and document schedule | To complete | To complete | To complete | To complete |
| Supply boundary, inspection and delivery scope | To complete | To complete | To complete | To complete |
Connect each conclusion to a document
- Identify the equipment: Record the proposed model, configuration and document revision. Check that the drawing, technical schedule and quotation describe the same scope.
- Match the evidence: For a test document, check the tested model or sample, ratings, test category and available pages. A management-system certificate addresses a different question from a product test record.
- Write down differences: Record missing evidence and exceptions against the buyer requirement. Do not change an unresolved item to an accepted item because another row looks similar.
- Close the review explicitly: Agree the revised technical schedule, drawings, test and inspection plan, responsibilities and remaining conditions. Keep the agreed versions together.
Questions worth resolving before acceptance
Can a catalogue value be treated as the offered guarantee?
Only when the selected offer and project technical documents expressly establish that value and its conditions. Otherwise retain it as a reference or an open item.
Does one certificate cover a different voltage or model?
Check the stated scope and the complete relevant document. Do not extend a sample result or a cover page to equipment outside its recorded scope.
What if a required item is missing?
List the missing item, the question, the responsible party and the document needed to close it. Clarify it before the relevant approval or commitment.
Public document examples
The following first-party references show how engineering scope and supporting documents are organized. Use the editions and evidence applicable to your own project.
- SGB-SMIT: cast-resin transformer planning guide
- Hammond Power Solutions: product specifications and technical documents
- IEC: prefabricated-substation standard scope
Bring the open items into one conversation
Share the proposed equipment, your requirement list and the questions still to resolve. Mingyu Ma coordinates the quotation inputs and the next technical discussion.